11.5 CHS Stadium Fiber Project - Pat Cuomo |
|
|
Strategic Plans:
|
|
Enclosure:
|
|
File Attachment:
|
|
Background and Summary:
|
CCS Athletics has requested a permanent solution for streaming games and events at the CHS Stadium. Other projects such as school security systems and the building of our private fiber network have taken priority over this request in the past. |
|
|
Funding:
|
|
Strategic Plan: |
Priority 4: Ensure effective and efficient operations
Target 8: 100% of school campuses and offices will be connected via Private Fiber Network.
|
|
|
Action Required: |
Funding for the fiber installation, hardware purchase, and supported technology is required. Estimated costs are $100,000 one time cost. |
|
|
Recommendation
|
Develop a short term solution with CCS Athletics to stream events for the 2025-2026 school year while a permanent solution with fiber, wired connections, and hardware can be implemented. The permanent solution will be future ready for additional athletic sites should CCS Athletics wish to pursue additional streaming options at different athletic fields. Please note that this recommendation only accounts for the fiber being run and that additional costs for hardware / labor / subscriptions would be required. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
 |
Dr. Royal Gurley - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Amanda Burns Moved, Member Dom Morse seconded to approve the Original motion 'to approve the allocation of $100,000 for the CHS Stadium Fiber Project from one-time fund balance. '. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | Lisa Torres | Yes | Dom Morse | Yes | Emily Dooley | Yes | Amanda Burns | Yes | Shymora Cooper | Yes | Nicole Richardson | Yes | Chris Meyer | Yes | |
|
|
|
|
|
|